Tuesday 23 July 2019

Maps of work done 2018-19

Aerial shot of 767 Gold Coast Springbrook Road


Project map

23rd Nov 2018 work
Lantana ‘smashing and hand ripping’ to remaining bund in zone 3a. Stems reduced to small pieces to allow follow up access. (Site Initiation, safety induction and site familiarisation included)
Primary spray run commenced through the Eastern side of the gully in zone 1. Significant Purple succulent treated. A primary woody weed and vine control run will be needed but due to the situation the spray work was prioritised so as to create less trampling and covering of the significant exotic ground covers.
Primary woody weed and vine control through the South West portion of zone 1. Selected large mature Camphor Laurel treated where healthy native understory exists. Significant Easter Cassia and Red Flowering exotic passiflora treated.
Primary over and under spray to Giant Devils Fig patch on the Southern boundary of zone 1 and 4. This was deemed important to get treatment to Madeira vine and Morning Glory amongst the Devil Fig patch.

20th December 2018 work
Cut & Paste, Crowning, Cut, Scrape & Paint and hand weeding to woody weeds and vines through the Southern side of creek line in zone 1.
Drill & Poison run to Southern side of creek line treating mature Cocas palm, Cadagi and Jacaranda. All specimens treated have numerous semi mature natives beneath the exotics canopy ready to replace.
Lantana ‘Smashing and hand ripping’ to small Lantana bunds. ‘Smashing’ of Lantana to free up Native stands and prepare areas for overspray works. Treatment of Climbing Lantana from Natives present. Lantana Overspray.
Initial client (David Straton) education with some works conducted in tandem. The previous treatment of the vast purple succulent is showing however more time is needed for chemicals to fully work before retreatment.


29th Jan 2019 work
Continuation of Primary Woody Weed and Vine Control Works through the Southern section of zone 1 pushing slightly into zones 3b and 4 where appropriate.
Previously over sprayed Lantana cages ‘Smashed’ down by brush hooks and cane knives to accelerate regeneration and recruitment to areas ‘opened up’.
Lantana ‘Smashing and Ripping’ along with some Cut & Paste to isolate existing native stands. Monoculture Lantana areas and exotic grass areas over sprayed.
Drill and Poison to selected mature Camphor Laurel where plentiful semimature natives exist beneath. Hand weeding, Cut & Paste and CS&P to all exotics within the understory of relatively intact native stands.


18th March 2019
Previously sprayed dead lantana frames broken down before continuing primary works to the south in remainder of zone 1 including control of exotic passionfruit vine, ipomoea indica, overspray of lantana and other woody weed control. Some follow up spray in area of work completed during previous visit



2nd May 2019 work
Completed primary woody and vine weed control in area at southern extremity of zone. Sprayed throughout area worked to date in zone incl. use of Starane to treat purple succulent, trad, Ipomoea indica, madeira vine and Giant devils figs. Hot mix was used primarily to treat exotic grasses, lantana, annuals and other secondary weeds


6th June 2019 work
Remainder of weeds were treated in area previously worked (Sthn zone 1) including hand pulling/ treating remainder of exotic passionfruit and lantana.   Work then commenced on the river bank to the north and area adjacent the access track which transects through the zone. Here we encountered an abundance of environmental weeds including Dutchman's pipe, residual lantana and annuals in amongst native ground cover. We conducted hand weeding, spray prep and spray treatment accordingly.


5th July 2019 work
Followed up on Camphor laurel stem injection and hand removed any remaining Dutchmans pipe along top of western creek bank.
Conducted initial woody and vine weed control in the area adjacent bottom of steep access track. Lantana was treated and reduced, large chinese celtis and camphor drilled and vines were treated.
Finished early due to rain


 12th July 2019 work
Completed vine and woody weed control in previously worked area where the day was called off early due to rain; then follow up sprayed. We then progressed further north in zone one to the other side of the pipe line. Here we covered the length of the slope and 20m in from the edge of vegetation. Heavy infestations of dutchman's pipe, cats claw vine and woody weeds including ochna and Brazilian cherry were encountered here


25th July 2019 work

Spent the morning doing follow up spray treatment in area of zone 1 where it was a bit woolly. Noteworthy frequent weeds where purple succulent, trad in the shady understory, lantana regrowth in more open patches; cats claw was less frequent.
Our afternoon efforts focused on cats claw and Dutchman's pipe along the current primary front line in zone 1. Scrape and paint treatment here is methodical and time consuming as the cats claw forms a dense mat in places.